Costs. Cost framework. Price information. Cost oriented price setting. Construction costs in Czech Republic. Participants in development. Work agreements. Negotiated prices. Costing aids. Construction costs. Overall cost estimate. Cost indicators of construction objects. Cost of construction object. Construction cost estimate. Data for cost estimate evaluation. Construction works costs. Costs of project preparation and engineering consultancy. Wage laws for engineers and other technical workers. History and evolution of costs in civil engineering in the Czech Republic. Basic knowledge of construction costing in other countries. Software for cost estimates. Prices of immovables.
Supervisor
Department
Institute of Structural Economics and Management (EKR)
Learning outcomes of the course unit
Students will gain the ability to:
- focus on pricing and types of prices in the Czech Republic,
- orientation in the sort of price information in the construction industry,
- to establish the price of the works in construction,
- calculate the cost of construction work,
- find out the value of building as a property.
Prerequisites
Knowledge of technology of constructions and works. Knowledge and skills of fundamentals of business economics, especially of areas of work, material, machines and equipment standartization, wages issues, coding and classification of construction production.
Co-requisites
Fundamentals of business economics, technology of structural works.
Recommended optional programme components
Not applicable.
Recommended or required reading
Not applicable.
Planned learning activities and teaching methods
The course is taught through lectures, practical classes and self-study assignments. Attendance at lectures is optional, but attendance at classes is compulsory.
Assesment methods and criteria linked to learning outcomes
The evaluation is complex. Students earn points during the term. The attendance, compile of examples and a written test are scored in the exercise (maximum 50 points). The activity is watched in the lectures during the term. The graded credit consists of a written test of theory (maximum 50 points) and reflects points gained from practice knowledge during the term in excercises (maximum 50 points). The whole maximum is 100 points.
Language of instruction
Czech
Work placements
Not applicable.
Course curriculum
1. Introduction.Price law.Price system.Price information.
2. Price of constructin. Complex budget of construction.
3. Price of building.Cost estimate of building.
4. Price of building.Systems for cost estimate in CR.
5. Price of building.Systems for cost estimating abroad.
6. Price of building work.Calculation formula.Comparative calculation.
7. Price of architects and engineers activities. Price of cost estimator activity.
8. Price of public order.
9. Price of property.Price law about propery valuation.
10.Price of property.Building.Land.Vegetation.Methods of valuation.
11.Price of property.Cost method of valuation.
13.Price of property. Yield method and comparative method of valuation.
Aims
To get knowledge about pricing with respect to knowledge from area of cost calculation and price setting in construction development. To acquire skills by working with cost estimate data and with up-to-date software applications for cost estimation and costing in civil engineering, that are used in construction practice. Basic knowledge about pricing of immovables.
Specification of controlled education, way of implementation and compensation for absences
Extent and forms are specified by guarantor’s regulation updated for every academic year.
Classification of course in study plans
- Programme N-P-C-SI (N) Master's
branch S , 1. year of study, summer semester, 3 credits, compulsory
- Programme N-P-E-SI (N) Master's
branch S , 1. year of study, summer semester, 3 credits, compulsory
- Programme N-K-C-SI (N) Master's
branch S , 1. year of study, summer semester, 3 credits, compulsory
Type of course unit
Lecture
26 hours, optionally
Teacher / Lecturer
Syllabus
1. Introduction.Price law.Price system.Price information.
2. Price of constructin. Complex budget of construction.
3. Price of building.Cost estimate of building.
4. Price of building.Systems for cost estimate in CR.
5. Price of building.Systems for cost estimating abroad.
6. Price of building work.Calculation formula.Comparative calculation.
7. Price of architects and engineers activities. Price of cost estimator activity.
8. Price of public order.
9. Price of property.Price law about propery valuation.
10.Price of property.Building.Land.Vegetation.Methods of valuation.
11.Price of property.Cost method of valuation.
13.Price of property. Yield method and comparative method of valuation.
Exercise
13 hours, compulsory
Teacher / Lecturer
Syllabus
1.-2. Introduction. Literature. Classifications. The general construction budget.
3.-4. Cost estimate of the building - selected works of main construction works.
5.-6. Cost estimate of the building - selected works of subsidiary construction works.
7.-8. Cost estimate of the building - set up.
9.-10. Calculation of selected construction work.
11.-12. Valuation of property - a model example.
13. Credit test.