Unified Methodology to Risk Management in Projects

Originální název

Unified Methodology to Risk Management in Projects

Anglický název

Unified Methodology to Risk Management in Projects

Jazyk

en

Originální abstrakt

In the submission is described the whole process of risk management that is possible to divide into six sub-processes (phases). In concrete, Risk management Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, Risk Response Planning, and Risk Monitoring and Control. In every of those phases we can use variety of methods, methodologies, techniques and tools. It depends on the concrete situation and general conditions in organizations. We distinguish both general methods (e.g. SWOT Analysis, Ishikawa Diagram), and more sophisticated methods (e.g. FMEA/FTA, HAZOP, SPC etc.) applied in a project. The paper demonstrates, by intuitive way, a complex procedure of risk management processes application. The main aim is to prevent risks and/or reduce their consequences in a project.

Anglický abstrakt

In the submission is described the whole process of risk management that is possible to divide into six sub-processes (phases). In concrete, Risk management Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, Risk Response Planning, and Risk Monitoring and Control. In every of those phases we can use variety of methods, methodologies, techniques and tools. It depends on the concrete situation and general conditions in organizations. We distinguish both general methods (e.g. SWOT Analysis, Ishikawa Diagram), and more sophisticated methods (e.g. FMEA/FTA, HAZOP, SPC etc.) applied in a project. The paper demonstrates, by intuitive way, a complex procedure of risk management processes application. The main aim is to prevent risks and/or reduce their consequences in a project.

BibTex


@inproceedings{BUT32110,
  author="Šárka {Květoňová} and Jitka {Kreslíková}",
  title="Unified Methodology to Risk Management in Projects",
  annote="In the submission is described the whole process of risk management that is
possible to divide into six sub-processes (phases). In concrete, Risk management
Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk
Analysis, Risk Response Planning, and Risk Monitoring and Control. In every of
those phases we can use variety of methods, methodologies, techniques and tools.
It depends on the concrete situation and general conditions in organizations. We
distinguish both general methods (e.g. SWOT Analysis, Ishikawa Diagram), and more
sophisticated methods (e.g. FMEA/FTA, HAZOP, SPC etc.) applied in a project. The
paper demonstrates, by intuitive way, a complex procedure of risk management
processes application. The main aim is to prevent risks and/or reduce their
consequences in a project.",
  address="Wroclaw University of Technology",
  booktitle="Proceedings of the  14th International Congress of Cybernetics and Systems of WOCS",
  chapter="32110",
  edition="NEUVEDEN",
  howpublished="print",
  institution="Wroclaw University of Technology",
  year="2008",
  month="september",
  pages="1--6",
  publisher="Wroclaw University of Technology",
  type="conference paper"
}